Exforsys

Online Training

Schedule Variance

This is a discussion on Schedule Variance within the Software Testing forums, part of the Testing category; Hi again... I want to know How do we calculate Schedule Variance? Regards Raman...


Go Back   Exforsys > Testing > Software Testing

Register FAQ Members List Calendar Search Today's Posts Mark Forums Read
  #1 (permalink)  
Old 09-27-2006, 06:38 AM
Junior Member
 
Join Date: Feb 2006
Posts: 16
Raman is on a distinguished road
Schedule Variance

Hi again...

I want to know How do we calculate Schedule Variance?

Regards
Raman
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #2 (permalink)  
Old 09-27-2006, 10:21 AM
qtptester's Avatar
Junior Member
 
Join Date: Aug 2006
Posts: 10
qtptester is on a distinguished road
Arrow Schedule Variance

When calculating Earned Value (EV) of a project, we multiply the planned value (PV) by the percentage work complete (% Com). I know this because many many many many textbooks tell me this and so do many many many guides to the project management body of knowledge.

To calculate the schedule variance (SV) one subtracts the planned value from the earned value.

So EV = PV x % Com
SV = EV - PV

So SV = (PV x % Com.) - PV [derived by substituting PV x % Com for EV]

If a project has a budget of R10,000 and to date we had planned to spend R7,000 and we have spent R7,000 and the project is planned to be 70% complete and is 70% complete then the schedule variance and the cost variance should be zero because, although it is only 70% complete, we are in fact on schedule and there is therefore no variance evident in the schedule.

According to this formula, however, this is not true. If I were to input the values -- as indicated by the formula -- the schedule variance would reflect as follows:

EV=7,000 x 70%
= R4,900

So the SV = R4,900 - R7,000
= R2,100 See what I mean?

Okay, so let's work out the SPI, because we know that if the project is running according to schedule and budget, then the SPI should be 1 i.e. 100%, right?

SPI = EV/PV
=4900/7000

Which is 1 i.e. 100%.

So, the only real way of attaining the "correct" answer would be to use the % work complete of the planned % work complete. So, it would be more appropriate to use 100% complete in the above example because the project is, in fact, 100% on track and that is how you derive the value earned to the project by investing the R7,000 in the work performed. If this is the case, I would recommend that another step be added into the process to determine the % complete of the planned % complete i.e.:

Actual % work complete/Planned % work complete [expressed as a percentage] and then using this in the formula for calculating the EV.


U can find this information via this link...........Expert Project Management - Earned Value Technique Sparks Discussion



Thanks
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
  #3 (permalink)  
Old 09-27-2006, 06:31 PM
Senior Member
 
Join Date: Mar 2005
Posts: 910
techguru is on a distinguished road
very nice explanation qtptester...
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiFurl this Post!
Reply With Quote
Reply

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads

Thread Thread Starter Forum Replies Last Post
IBM Walkin New Schedule - 8th July, Bangalore, Pune, Coimbatore lokeshm Experienced Job Seekers - India 0 06-27-2006 11:01 AM


All times are GMT -4. The time now is 03:57 PM.


Powered by vBulletin® Version 3.7.3
Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.1.0
Copyright 2004 - 2007 Exforsys Inc. All rights reserved.